The statement issued by the consortium Monday attributed the delays in making the nuclear plant operational to its Finnish client TVO, in an ongoing dispute over the construction of a nuclear plant in the Nordic country.
"TVO has not been able to demonstrate so far a clear operational organization to support the main pre-requisites," for the phases from the end of the reactor's construction to the start up of the plant, said Areva Monday, in a statement.
"If there is any further delay then it will be TVO's responsibility, we will ask them to respect their part of contract," said a spokesman for Areva.
Earlier this month,